The Engineering Department is tasked with overseeing planning, design and construction of the transportation, drainage, water and  wastewater Capital Improvement Projects (CIP) within the City of Rockwall.  Continual improvement of the City of Rockwall infrastructure is important in moving the City of Rockwall forward.



Traffic Signal Improvements
Ralph Hall Parkway and Steger Towne Road
Project Manager: Jeremy White, P.E., CFM
Current Status: Engineering Design
  • Installation of traffic signal steel pole/mast arm assemblies
  • Pedestrian count down heads
  • Internally illuminated street signs
  • Emergency vehicle & video vehicle detection
  • New ADA ramps, crosswalk striping, and stop bars.

S. Lakeshore Dr./Summit Ridge Dr. Reconstruction
(SH 66 to FM 740)
Project Manager: Jeremy White, P.E., CFM
Current Status: Engineering Design

E. Boydstun Ave. Reconstruction
(S. Goliad to Clark St.)
Throckmorton St. Reconstruction
(E. Boydstun Ave. to Bourn St.)
Project Manager: Jeremy White, P.E., CFM
Current Status: Final Engineering Design
Begin Franchise Utility Relocation first of March 2017

  • Advertise and Bid for Construction late Spring 2017
  • Street and City utility construction is scheduled
    to begin early Summer 2017
  • Public Meeting held June 29th, 2016, 6pm
    City Council Chambers, City Hall
  • Roadway reconstruction to concrete curb and gutter
    with 5’ sidewalk on each side.
  • Water Line Replacements
  • Wastewater Line Replacements


  • County Line Road Reconstruction
    (FM 3097 to Renee Dr.)
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • Public Meeting was held Monday, November 14th,
      2016 at 6:00pm in the City Council Chambers at City Hall, located at 385 South Goliad, Rockwall, TX 75087.
      County Line Road Exhibit
    • Roadway reconstruction to concrete curb and gutter
      with 5’ sidewalk on each side.
    • Drainage System Upgrades
    • Water and Wastewater Adjustments
    • Right-of Way Acquisition will be needed along the corridor.


    North Water Improvements
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Under Construction
    • Replacement of approximately 4,400 linear
      feet of water line to 8-inch diameter.
    • Miscellaneous pavement replacement
    • Culvert Installation
    • Driveway Repair
    • Approximate Construction Time 150 Calendar Days
    • Construction Plans

    Southside Elevated Tank Valve Installation
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Completed
    • Valve installation on the existing 16-inch
      concrete reinforced steel cylinder pipe at the
      Southside Elevated Storage Tank, includes preforming
      line stops and bypasses in order to install two
      16-inch butterfly valves.

    Greencrest 16" Water Line Replacement
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Completed
    • Replacement of existing 16 inch water line from W. Yellowjacket Ln. to the westbound frontage road of IH-30.Approximately 1,600 linear feet in length.
    • Street Pavement Replacement

    FM 3549 16" Water Line Relocation
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • The water line will be relocated, from a point approximately 550ft North of the IH-30 frontage road to a point adjacent to the northern property line of 670 Stodghill Rd (FM 3549), approximately 2800 feet in length and along FM 3549.
    • Water line being relocated due to TxDOT FM 3549 widening project.

    Stonebridge Lift Station Elimination
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design/Feasibility
    • Eliminating the aging existing wet/well/dry pit lift station by installing a new gravity sanitary sewer main from the existing NTMWD wastewater main to an existing wastewater manhole of S. Lakeshore Drive and Shore view Drive.
    • New services and cleanouts will be installed for the properties served by the new gravity mains.
    • The existing lift station will be decommissioned.

    Squabble Creek Lift Station Improvements/Quail Run Trunk Sewer
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • Lift Station Rehab includes replacement of existing pumps, pump starters, electrical room, transformer and generator.
    • Existing generator to be removed to Heath Street Pump Station.
    • Quail Run trunk sewer is 2,225 feet of 30 inch to 36 inch line that will by-pass Quail run lift station.

    Harborview Sanitary Sewer Relocation
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Completed
    • Relocation of approximately 250 linear feet of 8-inch
      wastewater main
    • Relocation of approximately 305 linear feet of 6-inch
      wastewater force main.

    Signal Ridge Sanitary Sewer Pipebursting
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Under Construction
    • Pipebursting approximately 1,200 linear feet of existing 10 inch diameter PVC wastewater main to 14 inch diameter main.
    • Project includes removal and replacement of existing manholes and reconnection of existing services.
    • Project in located to the west of the Hilton, Portofino and Signal Ridge.

    Munson Street Sanitary Sewer Improvements
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Completedn
    • Replace existing wastewater main with approximately 600 feet of 8 inch PVC pipe by open cut.
    • Including waterline connections at Star Street and Tyler Street.
    • Asphalt Road reclamation after the utilities are complete.

    Lake Forest Erosion Control
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Completed
    • 134 linear feet of rock anchored, precast concrete "big block" retaining wall with a maximum height of 16.5 feet, articulated concrete block mattress, and other miscellaneous items.