Mission
The Engineering Department is tasked with overseeing planning, design and construction of the transportation, drainage, water and  wastewater Capital Improvement Projects (CIP) within the City of Rockwall.  Continual improvement of the City of Rockwall infrastructure is important in moving the City of Rockwall forward.



Traffic Signal Improvements
Ralph Hall Parkway and Steger Towne Road
Project Manager: Jeremy White, P.E., CFM
Current Status: Under Construction
  • Installation of traffic signal steel pole/mast arm assemblies
  • Pedestrian count down heads
  • Internally illuminated street signs
  • Emergency vehicle & video vehicle detection
  • New ADA ramps, crosswalk striping, and stop bars.

S. Lakeshore Dr./Summit Ridge Dr. Reconstruction
(SH 66 to FM 740)
Project Manager: Jeremy White, P.E., CFM
Current Status: Engineering Design

E. Boydstun Ave. Reconstruction
(S. Goliad to Clark St.)
Throckmorton St. Reconstruction
(E. Boydstun Ave. to Bourn St.)
Project Manager: Jeremy White, P.E., CFM
Current Status: Final Engineering Design
Begin Franchise Utility Relocation first of March 2017

  • Advertise and Bid for Construction late Summer 2017
  • Street and City utility construction is scheduled
    to begin Fall 2017
  • Public Meeting held June 29th, 2016, 6pm
    City Council Chambers, City Hall
  • Roadway reconstruction to concrete curb and gutter
    with 5’ sidewalk on each side.
  • Water Line Replacements
  • Wastewater Line Replacements


  • County Line Road Reconstruction
    (FM 3097 to Renee Dr.)
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • Public Meeting was held Monday, November 14th,
      2016 at 6:00pm in the City Council Chambers at City Hall, located at 385 South Goliad, Rockwall, TX 75087.
      County Line Road Exhibit
    • Roadway reconstruction to concrete curb and gutter
      with 5’ sidewalk on each side.
    • Drainage System Upgrades
    • Water and Wastewater Adjustments
    • Right-of Way Acquisition will be needed along the corridor.



    FM 3549 16" Water Line Relocation
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • The water line will be relocated, from a point approximately 550ft North of the IH-30 frontage road to a point adjacent to the northern property line of 670 Stodghill Rd (FM 3549), approximately 2800 feet in length and along FM 3549.
    • Water line being relocated due to TxDOT FM 3549 widening project.

    Stonebridge Lift Station Elimination
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design/Feasibility
    • Eliminating the aging existing wet/well/dry pit lift station by installing a new gravity sanitary sewer main from the existing NTMWD wastewater main to an existing wastewater manhole of S. Lakeshore Drive and Shore view Drive.
    • New services and cleanouts will be installed for the properties served by the new gravity mains.
    • The existing lift station will be decommissioned.

    Squabble Creek Lift Station Improvements/Quail Run Trunk Sewer
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • Lift Station Rehab includes replacement of existing pumps, pump starters, electrical room, transformer and generator.
    • Existing generator to be removed to Heath Street Pump Station.
    • Quail Run trunk sewer is 2,225 feet of 30 inch to 36 inch line that will by-pass Quail run lift station.

    Memorial Gravity Trunk Sewer
    Project Manager: Jeremy White, P.E., CFM
    Current Status: Engineering Design
    • Memorial trunk sewer is 3,050 feet of 18 inch wastewater line that will by-pass Memorial lift station connect into the proposed Quail Run trunk sewer
    • Trunk sewer will allow for the decommissioning of the Memorial and Lakeview Summit Lift Stations.

     
    No Current Projects Underway
    CIP Interactive Map
    CIP Interactive Map








    background image